Status
Completed
WhenÂ
Jul – Dec 2010
Where
Göteborg
Manufacturing of pollarfundament and demolition of the concrete ramp in progress. Concrete ramp (500m2) will be removed and 70 concrete piles cut at the bottom. In total there are about 1,000 tons of concrete to be demolished and no material gets into the water. Ship Tempering continues as usual.