New pier in Vikhögs Hamn

By 8 February, 2016March 29th, 2016Projekt, SSE

Status
Completed

When
2015

Where
Vikhögs Hamn

– Dredging to -2,5 meters
– Piling/frame of new breakwater/pier
– Completing piers on the docks
– Delivery of decking, screws and bolts

Resources:
– 4 man team
– Sjögrip
– Pontus
– Björnpråmen