Demolition of wind park Yttre Stengrund

By 27 January, 2016March 24th, 2016Projekt, SSE

Pictures from Vattenfall’s website

Status
Completed

When
2016

Where
Vattenfall’s wind farm Yttre Stengrund, Karlskrona

SSE as prime contractor has successfully completed the dismantling of five wind turbines. We have dismantled and lifted down the rotor blades, turbine and tower. We have aslo chopped off foundations in level with the seabed.

This is the first time in the world that an offshore wind farm gets dismantled!

Link to Vattenfall’s news article:

http://news.vattenfall.com/en/article/yttre-stengrund-memory

Link to Vattenfall’s press release:

http://corporate.vattenfall.se/press-och-media/pressmeddelanden/2016/varldens-forsta-rivning-av-en-havsbaserad-vindkraftpark-nu-slutford/