KVV8, VĂ€rtan, Stockholm

By 15 August, 2014August 20th, 2015Projekt, Sventab

Status
Completed

When 
Sommaren 2014

Where 
Stockholm

SVENTAB perform on behalf of JM a bulldozer, leveling the ground, reinforcement and dense casting of several contiguous groove pits KVV8, Stockholm.

The workforce consisted of several Dive Team who worked in shifts / 7 days a week. 0500-2200 during the summer 2014.

We have Toyoexcavated, rinsed steel sheet pile, leveled the ground, armored ink UV casting.